The resultant flash flooding overwhelmed the drainage system, causing c£20m damage. Teaching facilities, accommodation blocks, various sports halls and even a castle were affected.  Contents, including expensive IT infrastructure and laboratory equipment, were also damaged.  Despite the scale of the loss, we enabled the University to function throughout repairs.  

We immediately deployed an experienced team from Sedgwick, one of our panel loss adjusters, and implemented a collaborative project management approach to ensure all stakeholders were involved.  Sedgwick’s Major Loss Regional Manager attended site the following morning, along with representatives from the University and the brokerage, Gallagher.  The sheer scale of damage was likened to ten interdependent major losses, and there were serious challenges to overcome:

  • key facilities had suffered significant damage
  • different forms of construction
  • no uniformity in the pattern and distribution of damage 
  • imminent graduation ceremonies 
  • the need to maintain occupation and use of buildings 
  • presence of asbestos 
  • buildings with listed status 
  • short time available to complete repairs.
It was vital to agree initial areas to prioritise.  The most pressing was the graduation ceremony that day.  A major clean-up operation was undertaken, with unaffected buildings converted into temporary halls.  We also recognised that communication, creative thinking and collaboration were the keys to success, so we agreed to speak daily and meet weekly.

Working closely with all stakeholders, we rapidly agreed a series of innovative solutions, including:

  • accelerated purchasing programme 
  • early introduction of specialist contractors and consultants 
  • accelerated drying techniques 
  • focus on restoration over replacement 
  • an appropriate contractor for each building based on its construction 
  • phased approach to repairs – cosmetic repairs were deferred 
  • out of hours working to minimise disruption 
  • student timetable altered to optimise use of undamaged areas.
Understanding the scale of the damage, we made an early interim payment of more than double the requested amount within a couple of days to cover the first phase of work. Working collaboratively with our loss adjusters, we co-ordinated more than 100 specialists including major loss adjusters, restoration consultants, project surveyors, building contractors, asbestos specialists, IT and environmental adjusters and business interruption accountants.  We also contracted a listed building consultant to work with Historic Environment Scotland to pre-empt its recommendations and prevent delays. Our approach ensured the university was fully operational within just nine weeks, in time for the new academic year.  
Alasdair Tweedie, Director of Property Management, University of Stirling
Graham Gibson, Chief Claims Officer, Allianz
Iain Binning, Loss Controller, Gallagher brokers